INSTALLED THE BIGGEST SUMP CAISSON
ON B1 LEG OF BHF (BHN) PLATFORM FOR MAZGAON DOCK LTD (MDL).
DIA: 1981 MM (OD), LENGTH 70 M, WEIGHT 90 TONS. |
EXCAVATION OF OLD WOODEN JETTY AT KASARA CHANNEL FOR MDL. BY UNDERWATER DRILLING OF HOLES & USE OF EXPLOSIVES. |
REMOVAL OF ROCKS BY CONTROL BLASTING &
EXCAVATION BY BARGE MOUNTED CRANE
AT KASARA CHANNEL FOR MDL |
| |
|
|
 |
 |
 |
(CLAMP-ON-PROJECT AT PANNA PB &
PF PLATFORM FOR BGPEI) |
INSTALLATION OF SINKERS, MOORING CHAINS & MARKERS BUOY FOR INDIAN OIL CORPORATION LTD.
AT KANDLA (GUJARAT). |
DIVING WORKS ON PLEM STRUCTURE BY DEPLOYING 3 POINT MOORING SYSTEM ONBOARD M.V.FERROMINA HARVEST FOR REPLACEMENT OF BALL VALVES AND INSTALLATION OF ANODES AT – 47MSW ON PLEM
AT R-15A, HEERA FIELD. |
| |
|
|
 |
 |
 |
DIVING WORKS ONBOARD M. V. ANVEKSHAK AT SM PLATFORM FOR REPLACEMENT OF STUDS ON CONDUCTOR CLAMPS
AT –57 MSW FOR ONGCL. |
ANNUAL MAINTENANCE OF SPM AT OFFSHORE, PANNA FIELD FOR BG EXPLORATION & PRODUCTION INDIA LTD.
FOR YEAR 2003, 2004, 2005. |
UNDERWATER CUTTING WORKS BY USE OF BROCO CUTTING SYSTEM AT GANGA RIVER BRIDE FOR HYUNDAI. |
| |
|
|
 |
 |
 |
| DIVING WORKS AT MAHI BAJAJ SAGAR DAM, BANSWARA, RAJASTHAN. |
EXCAVATION OF NATURAL MOULD |
UNDERWATER ROCK BLASTING WORKS |
| |
|
|
 |
 |
 |
| EXCAVATION OF BLASTED ROCK DEBRIS BY USE OF TROLLEY CRANE AND TRANSPORTING IT TO THE DUMPING GROUNDS. |
Double bunking of tanker Tanker changeover Operation.
Correction of hawser & floating hose for transferring of oil.
For British Gas at Panna Field. |
NORMER BUOY. Salvage of damage floating riser, pipeline & normer sub sea. Inspection, cleaned fouled wine rope recovery of buoy on board SEA STALLION BARGE. |
| |
|
|
 |
 |
 |
Divers with Sub-Sea Production buoy during
Recovery operation. |
Inspection and measurement of leakage on PLEM –
Pipeline, at Panna field |
INSTALLATION OF 5’ JETTING PIPE LINE & CLAMPS
FOR RIG# PERRO NERRO 3 FOR SAIPEM |
| |
|
|
 |
 |
 |
INSTALLED 2 NOS 30” AND 1 NOS 48” RISE FROM THE JETTY TO THE PIPE LINE FLANGE.
HYDRO TIGHTENED OF ALL RISER NUT BOLTS ON BOTH FLANGES AT WATER DEPTH20 FEET
AT APL RELIANCE JETTY JAMNAGAR. |
INSTALLED SPM NO. 05 FOR RELIANCE AT JAMNAGAR. |
INSTALLATION OF FLOATING JETTY
FOR INDIAN OIL CORPORATION LTD.
AT KANDLA (GUJARAT). |
| |
|
|
 |
 |
 |
CLAMP-ON PROJECT AT PANNA PB & PF
PLATFORM FOR BGPEI |
CLAMP-ON PROJECT AT PANNA PB & PF
PLATFORM FOR BGPEI |
Installation of Barge Bumpers & Riser Protectors
for ONGC BBLRP Project |
| |
|
|
| |
 |
|
| |
Installation of Barge Bumpers & Riser Protectors
for ONGC BBLRP Project |
|